Statoil Yttergryta

Norway_StatoilHydroYttergryta

Norway Midgard 6507/11

Landmark: Subsea structure built and installed before drilling of exploration well

The ISS was installed in January 2007.The flow base and PLEM were scheduled to be installed June 2008, the tie-in in August 2008 and the completion was scheduled for October 2008. Start-up was set for January 2009. Yttergryta is tied-in to Midgard X on the Aasgard field.

  • One HXT system
  • One flow base
  • One integrated satellite structure with SSP
  • One pipeline end manifold with WGM
  • One nearby protection structure
  • One umbilical 3.7 miles (6 km)
  • Termination heads, tie-in and pigging equipment
  • Fail-close valve skid