Landmark: Subsea structure built and installed before drilling of exploration well

The ISS was installed in January 2007.The flow base and PLEM were scheduled to be installed June 2008, the tie-in in August 2008 and the completion was scheduled for October 2008. Start-up was set for January 2009. Yttergryta is tied-in to Midgard X on the Aasgard field.

Water Depth: 298 m (978 ft)
Tree Pressure: 10000 psi
Tree Type: HXT
Tree Count: 1
Tree Bore Size: To be decided upon"
Hydrocarbons: Gas