Petronas Chinguetti Phase II

Mauritania, West Africa

Landmark: Petronas Chinguetti Phase II is the first subsea project in Mauritania.

The Chinguetti field is located in Deep Water Block 4 of PSC B, located 50 miles (80 km) west of the Mauritania coastline some 56 miles (90 km) from the capital, Nouakchott.

Phase 1 of the field was developed with subsea wells, manifolds, flexible flowlines, umbilicals and risers tied back to the permanently moored turret-style FPSO with 1.65 mbbl storage in 2,280 ft (695 m) water depth. Initial production of 75,000 bpd is anticipated from six wells. Offloading is by way of trading tankers tandem moored. The Phase I subsea trees were of the OXT design, which was a novel concept of concentric completion which allows the tubing string to be run at the same time as the subsea tree, thus saving trip times.

Phase II of the Chinguetti field development includes subsea hardware supplied under a frame agreement with Woodside Energy Ltd and FMC Technologies Australia. The subsea trees are of the EVXT design as supplied on the Vincent project, but modified to interface with the HOST® manifolds supplied in Chinguetti Phase I.

First oil was produced from the field in February 2006 with an FPSO.

Woodside Mauritania was sold to Petronas in December 2007, a Malaysian oil company based in Kuala Lumpur.

Phase I:

  • Fourteen wellhead sets UWD15
  • Thirteen OXT systems (7 production + 1 spare, 4 water injection and 1 gas injection)
  • Three host templates and manifolds
  • Workover riser system including drillpipe riser (Grant Prideco)
  • Workover controls
  • Topside controls
  • Intervention tooling
  • Support landing structure for west navigator
  • Umbilical termination units
  • Flowline termination heads
  • Overtrawlable structure (gas injection well)
  • System integration, testing, installation assistance, service and maintenance

Phase II:

  • Four production Enhanced Vertical Subsea Trees (EVXT)
  • Two injection Enhanced Vertical Subsea Trees (EVXT)
  • Six PGBs and HOST
  • Modification of existing Chinguetti Phase I WOCS HPU
  • Modification of existing Chinguetti Phase I WOCS Umbilical Reeler
  • Tubing Hanger Running Tool Umbilical Reeler
  • Tubing Hanger Running Tool HPU
  • Four termination heads for ROVCON
  • One simplified landing string
  • Stack-up testing in Singapore for new type XT